In brief
A licence for alterations is the landlord's written consent for works that your lease does not let you carry out freely. In a leased warehouse or factory, a new partition run is often one of those works. The licence usually sets out what you may build, how, and whether you must remove it when the lease ends.
Contents of this post
It is easy to assume a few bolted-down partitions are their own business. You are paying the rent, after all, and mesh comes out again. But your lease may say otherwise, and the document that sorts it out is a licence for alterations.
This post explains what a licence for alterations is, when you are likely to need one for partition work, what a landlord can reasonably ask for, and how to keep it from holding up the job. It is general information, not legal advice, so have your solicitor read your own lease.
What the licence actually is
A licence for alterations is a written consent from your landlord to carry out works that the lease restricts. It is usually a short formal document, often signed as a deed, sitting alongside the lease.
It normally covers three things:
- The works: described in words and usually by reference to drawings, so there is no argument later about what was agreed.
- The conditions: how the work is done, by whom, and with which approvals.
- The end of the lease: whether you must take the works out and put the unit back as it was.
Once it is signed, you can carry out exactly those works without breaching the lease. Anything beyond the drawings needs fresh consent.
How your lease decides whether you need one
Leases deal with alterations in different ways, and the wording matters more than the size of the job. Have a look at the alterations clause before you ask anyone for a price.
| What the lease says | What it means for a partition |
|---|---|
| Alterations are not allowed at all | You need the landlord to agree to vary or waive the clause. They do not have to. |
| No alterations without consent | You need consent first. |
| No alterations without consent, not to be unreasonably withheld | You need consent, and the landlord must act reasonably. |
| Non-structural or demountable partitions allowed freely | You may not need a licence at all, though you may still have to tell the landlord. |
That last row is worth checking for. Some modern leases let tenants put up demountable partitioning without formal consent, which suits mesh and other bolt-down systems.
The rule that stops an unreasonable refusal
There is a statutory safety net in England and Wales. Section 19(2) of the Landlord and Tenant Act 1927 says that where a lease bars improvements without the landlord’s consent, that consent is not to be unreasonably withheld.
The same section lets the landlord ask for some things in return. They can require a reasonable sum for any damage to, or loss of value of, the premises or neighbouring property, and their reasonable legal and other expenses. Where the improvement does not add to the letting value, they can also ask for an undertaking to put the premises back as they were, where such a requirement would be reasonable.
In other words, the landlord cannot simply say no to a sensible partition, but they can make you pay their costs and agree to take it out.
What landlords usually ask for
Expect your landlord’s surveyor or solicitor to want some or all of the following before they sign:
- Drawings and a specification of the partition, with fixing details into the slab or structure.
- Building control approval where the work is building work, and a copy of the completion certificate afterwards.
- Insurance details for the installer.
- A reinstatement clause, so you remove the partition and make good the floor at the end of the lease.
- Their costs, which the tenant often pays.
Building rules sit alongside the licence
A licence deals with the landlord. It does not deal with the law on buildings, and you need both.
Under regulation 3 of the Building Regulations 2010 (England and Wales), a material alteration is building work. That covers work that would leave the building failing, or failing further, against certain requirements, including structure and the fire rules on escape and internal fire spread. A partition that cuts across an escape route or forms part of a fire compartment can fall into that, so check with building control.
Look at the fire risk assessment too. Under article 9 of the 2005 Fire Safety Order, whoever is the responsible person for the premises reviews the assessment when there has been a significant change in the premises. New walls change how people get out, so a fresh look is usually needed. Your landlord may well ask to see that you have done it.
A worked example
Say you lease a 2,000 m² storage unit and want a locked mesh store of about 40 m of run in one corner, with one sliding door.
- You read the lease and find “no alterations without the landlord’s consent, such consent not to be unreasonably withheld”.
- You get a layout drawing from an installer and send it to the landlord’s surveyor with a short note on fixings.
- The store does not touch an escape route, so building control confirms it is not building work. You note the change in the fire risk assessment anyway.
- The landlord grants a short licence with a reinstatement clause and asks you to pay their surveyor’s fee.
How long that takes depends on the landlord and their advisers, but a clear drawing sent early gives them everything they need to answer.
How to keep it moving
Delays often come from vague information. Give the landlord a proper drawing, say whether the system is demountable, and offer reinstatement up front if you are happy to take it out at the end. Bolt-down mesh and fabric systems are easier to agree to for exactly that reason.
When you are ready to price the job, ask the installer for a dimensioned layout drawing first: it is the one document your landlord, building control and your industrial partitioning company quotes all depend on.