The main machine guarding rule in Great Britain is regulation 11 of PUWER, the 1998 regulations on providing and using work equipment. It requires employers to stop people reaching dangerous parts of machinery. It sets an order to follow, starting with fixed guards that enclose the danger.

Contents of this post
  1. The regulation that does the work
  2. The order you work through
  3. Where perimeter fencing fits
  4. The code of practice and the standards
  5. New machines and the supplier’s duty
  6. A worked example
  7. What to give a guarding installer

If you run a factory floor, you may think of guarding as something that arrives bolted to the machine. Often it does. But the duty to make sure people cannot reach the dangerous parts sits with you, the employer using the machine, and that duty comes from one regulation in particular.

This post sets out what that regulation says, how HSE expects it to be applied, and where fencing and partitions fit in.

The regulation that does the work

PUWER, the 1998 regulations on the provision and use of work equipment, cover almost any equipment used at work. Regulation 11 deals with dangerous parts of machinery.

It requires employers to take effective measures to prevent access to any dangerous part of machinery, or to stop the movement of that part before any part of a person enters the danger zone. “Dangerous part” means anything that could injure someone: moving blades, rollers, presses, the reach of a robot arm.

The order you work through

Regulation 11 does not let you pick any measure you like. It sets a hierarchy, and you move down it only where the step above is not practicable.

Order Measure What it looks like on the floor
1 Fixed guards enclosing every dangerous part Bolted covers, perimeter fencing round a cell
2 Other guards or protection devices Interlocked doors, light curtains, pressure mats
3 Protection appliances Jigs, holders, push-sticks
4 Information, instruction, training and supervision Signs, induction, a supervisor’s check

The fourth line applies alongside the others, not instead of them. Training does not replace a guard where a guard is practicable.

Where perimeter fencing fits

A mesh fence round a robot cell is a fixed guard, so it sits at the top of the list. That is why it is held to a different standard from a mesh partition that simply divides space.

Treat the fence as part of the machine’s safety design rather than as building work. Its height, the size of the mesh openings and how far it stands from the hazard all affect whether someone could reach in or over. Those relationships are set out in BS EN ISO 13857, and a guarding designer applies them to your machine.

Access doors into the cell are movable guards. They are normally interlocked so the machine stops before anyone can reach the danger, which puts them on the second line of the table.

The code of practice and the standards

HSE publishes an Approved Code of Practice and guidance on PUWER, known as L22. It explains how to meet each regulation, and following it is a recognised way of showing you have complied.

For the guards themselves, the main standards are:

  • BS EN ISO 14120: general requirements for the design and construction of fixed and movable guards.
  • BS EN ISO 13857: safety distances to stop arms and legs reaching hazard zones.

Standards are not law in themselves, but working to the relevant ones is the usual way to show a guard is effective. Our post on BS EN ISO 14120 goes into that standard in more detail.

New machines and the supplier’s duty

If you are buying a new machine, the supplier has duties too. The Supply of Machinery (Safety) Regulations 2008 require machinery placed on the market to be safe, which includes suitable guarding.

But again, it will depend on the setup. A machine safe on its own may not be safe once it sits in a cell with a conveyor and a robot, which is exactly where site fencing comes in. Ask the supplier what guarding comes with the machine before you order fencing separately.

A worked example

Say you are installing a palletising robot at the end of a packing line.

  1. The machine risk assessment shows the robot’s reach and the points where pallets enter and leave.
  2. A fixed perimeter fence is practicable, so that is the starting point.
  3. The fence height and distance from the robot are set using BS EN ISO 13857.
  4. A maintenance door is interlocked with the robot controls, and light curtains cover the pallet openings where a fixed guard would stop the line working.
  5. Operators are trained on the door and the reset procedure.

Each step follows the order in regulation 11, and each measure covers what the one above could not.

What to give a guarding installer

Have the risk assessment, layout drawings showing the moving envelope, and a list of access points ready. The installer can then design a fence that meets the standards rather than one that just looks the part.

Got a cell or a line that needs fencing? The form below takes a minute to fill in.

Rules and guidance we drew on

Ask for a partition quote

We look for an installer who fits this kind of system near your site and tell you who they are before any of your details go to them. There is no charge to you.

Step 1 of 3
Where is the building?
Get a quote